Kings Park resurfacing disruptions schedule

Here’s the latest Main Roads Western Australia schedule on the works due for completion by the end of the year.

Closure 1: Lovekin Drive between Poole Avenue and Forrest Drive East; completed.

Closure 2: May Drive from Fraser Avenue to Saw Avenue; to be completed on 30 September.

Closure 3: Saw Avenue to Zamia Cafe – 1 October to mid-October

Closure 4: Zamia Cafe to Poole Avenue – October/November 2024, date to be advised.

Main Roads advises: “Rolling closures will be required in November and December to complete resurfacing on this road network. Dates and locations will be confirmed closer to those works as they are weather-dependent. All works timeframes are subject to change due to weather and operational conditions.”

More info is here: Kings Park Resurfacing and Road Shoulder Project | Main Roads Western Australia

Tim Roach (Chair)

Elected Director | Off Road

Tim has been in senior leadership and strategic development roles for more than 20 years and is currently a project risk consultant, and a part time academic at Edith Cowan University.

He is a past Director of Executive Education in the School of Business and Law at Edith Cowan University and Assistant Commissioner and General Manager in the public service. He is an Accountant (FCPA) and previously sat on the Divisional Council of CPA Australia. Tim has been involved in racing mountain bikes, BMX and triathlon for many years, both as a father of two children who race and as a past and current bike racer.

Helen Sadler (Deputy Chair)

Independent Director

Helen is a Town of Cottesloe councillor and is the current Chair of WestCycle’s Transport Advisory Group.

A medical doctor, Helen is a strong active transport advocate with a focus on health outcomes and social well-being.