APRIL 2020 MAJOR WORKS AND INFRASTRUCTURE UPDATES

23 April 2020

Major Works and Infrastructure Updates

There are plenty of new places to ride to look forward to this weekend and in the coming months with the opening of the Kwinana Freeway and Tonkin Highway PSP projects and others nearing completion. Below is a summary of the latest news and updates from around WA.

 

Now Open

Kwinana Freeway Principal Shared Path – Farrington Road to Kentucky Court
Opened 20 April 2020
The Kwinana Freeway PSP has been widened and upgraded as part of the Kwinana Fwy Northbound Widening and Murdoch Drive Upgrade Projects. As part of this project, the PSP was widened to 4m and built slightly west of where it currently sits, to the edge of the road reserve and the neighbouring properties. Some of the PSP access points have changed, with some upgraded and others closed permanently.

Please note that the detour from Kentucky Court to Armadale Road will remain in place to allow the construction of the Armadale-North Lake Rd Bridge.

More information https://westcycle.org.au/kwinana-fwy-psp-diversion-phase-7-cockburn-central-to-hope-road-north-lake-2019/

Tonkin Highway Principal Shared Path Construction – Ellenbrook to Muchea
Opens 23 April 2020 (today!)
The opening of this third and final section, completes the 40km+ link from Railway Parade in Bayswater to Muchea with a fully separated 4m-wide Principal Shared Path that also connects to the Reid Highway PSP that is currently being extended between Altone and West Swan Roads.

Please note that Muchea is a part of the Wheatbelt region and intrastate travel restrictions are still in place.

More information: https://westcycle.org.au/tonkin-hwy-psp-construction-bayswater-to-muchea/

RAC Arena Path Update
The accessway on the northern side of RAC Arena has reopened whilst there are no events at RAC Arena. Future options to improve safety around the arena during event-times are being explored and will include managed closures of the accessway during event times. We will provide further updates and share the schedule of works once these details have been finalised.

More information https://westcycle.org.au/rac-arena-path-update-december-2019/

Under Construction

Mitchell Freeway Principal Shared Path Upgrade – Richmond St to Goody Close
Scheduled to open late-April 2020
The update of the PSP is progressing well. Upgrades include resurfacing and widening the path to up to 3.6m

More Information https://westcycle.org.au/additional-works-announced-on-the-mitchell-freeway-psp-2019/

Mitchell Freeway Principal Shared Path Construction – Goody Close to Telford Cres
Scheduled to open in May 2020.
The full section of PSP from Vincent Street to Telford Crescent is scheduled to be complete in May 2020. When complete, this PSP will feature an overpass at Scarborough Beach Road, an underpass at Hutton St and WA’s first separated path featuring a 4m cycling-only and a 2m walking-only path between Roberts St and Glendalough Station.

More Information https://westcycle.org.au/mitchell-fwy-psp-construction-2018/

Reid Highway Principal Shared Path Construction – Altone Road to West Swan Road
Scheduled to be completed mid-2020.
Construction is underway and is progressing well. When complete, this PSP will connect to the West Swan Road Shared Path to the east, the New Tonkin Highway (Northlink) Principal Shared Path to the west and will also connect to the Drumpellier Dr (New Lord Street) shared path.

More Information https://westcycle.org.au/reid-hwy-psp-extension-2019/

Roe Highway Principal Shared Path Construction – Berkshire to Kalamunda Road.
Scheduled to be complete by early-2021.
Construction of the southern section between Maida Vale and Berkshire Roads is progressing well. We have asked Main Roads and the contractors to include an upgrade of an existing ~400-500m section of path from Berkshire Road into the scope of this project and open sections of the PSP as soon as practicable. Further details will be shared once they are made available.

More information https://westcycle.org.au/roe-hwy-psp-extension-high-wycombe-2019/

Welshpool Road East Path Upgrade- Roe Highway to Hale Rd
Scheduled to be completed June 2020
Works to upgrade the sub-standard existing path west and east of the bridge-over-rail on Welshpool Road East linking the new path to Hale Road

More information https://www.mainroads.wa.gov.au/UsingRoads/PedestriansCyclists/Pages/PedestriansCyclists.aspx 

Recently Announced

Midland Railway Principal Shared Path Construction – Success Hill Train Station
Expected completion June 2020
Main Roads is about to start constructing a short section of the Perth-Midland Principal Shared Path adjacent to Success Hill Train Station in Bassendean.
This project includes new lighting and rest bays. Work is expected to start in May 2020 and be finished by the end of June 2020.

More information https://westcycle.org.au/midland-railway-psp-construction-success-hill-2020/

Kwinana Freeway Principal Shared Path Construction – Leach Highway to Mt Henry Bridge
Expected completion 2021/22
Main Roads is planning for the final link in the Principal Shared Path network along the Kwinana Freeway, between Leach Highway and Mount Henry Bridge, through the southern suburbs of Brentwood and Mount Pleasant.

Design is underway and is expected to be completed by mid-2020. Subject to approvals, construction could commence in the final quarter of 2020 and be finished in 2021

More information https://westcycle.org.au/kwinana-fwy-psp-construction-mount-pleasant-2020/

 

Path Maintenance

Here are some sections of shared path that have received some rehabilitation recently.

Mitchell Freeway PSP – near Tuart Road Overpass, Duncraig

Graham Farmer Freeway PSP – near Goodwood Parade Boat Ramp

Leederville Pde/Vincent Street shared path

 

To keep up to date with the progress of these and other projects in WA, please visit https://westcycle.org.au/major-works-updates/